Laser Cutter. Laser Focus.

Ahead of a new DfE framework school build that amalgamated 2 sites, we conducted multiple surveys of old and new FF&E to reduce costs and allow the new spaces to be designed.

 

We undertook the labelling of over 3000 items, provided storage, crates and coordinated site access across two separate sites and managed removal operatives over a 9 day period.

 

This involved commissioning and managing a specialist move of a 300kg laser cutter from the first floor of the existing building into the new one.

 

The volume, range and specialist nature of the moving parts of the decant amounted to a considerable undertaking.